Project Description

GETS successfully executed the development of a comprehensive pipeline and export system, ensuring seamless integration with existing infrastructure. The project scope included routing flowlines and constructing a 96 km export oil pipeline, connecting the Early Well Test (EWT) facility to the existing export pipeline. Additionally, the project encompassed the establishment of telecommunication systems at the temporary camp.

As part of the execution, GETS installed a 12″ export pipeline, carried out extensive brownfield and greenfield work at NC-115B, and implemented a fiscal metering skid, metering control room, substation, and DG set, alongside the integration of critical telecommunications infrastructure.

The installation of the 96 km pipeline required a wide range of specialized activities, including:

  • Civil, mechanical, electrical, coating, and painting works
  • Stringent quality control measures, including hydrotesting and pre-commissioning
  • Comprehensive design support and development of detailed method statements
  • Procurement of materials and management support
  • Supply of skilled manpower
  • Complete handover procedures

Through meticulous planning and execution, GETS ensured the project was delivered to the highest industry standards, reinforcing our commitment to excellence in oil and gas infrastructure development.